Under Blue Skies, Bridge Truss is Successfully Moved

After months of preparation, the team hired by the Vermont Agency of Transportation to rehabilitate the historic Checkered House Bridge, moved a 1928-era truss 12.5 feet to widen and improve the bridge for 21st century travel needs.

It took about 25 workers one and a half days to complete the task.

Immediately after the move work began to install new steel extensions that will reconnect the north truss back to the 1928 bridge.

Read the News Release

Visit the Checkered House Bridge Website

This entry was posted in Bridge Design/Const., Bridge Pres. Apps., Featured, General News, New Technology, News, Pavement Design/Const., Pavement Pres. Apps.. Bookmark the permalink.